12 Problems with Software Estimation

Software estimation is hard, really hard, but still many software companies rely heavily on software estimations. I will present twelve big problems that come with software estimation. The list could easily have 20 or 30 problems, but I limited the list to only twelve problems.

I will not suggest any solutions to these problems yet; that is the topic of another post.

1. It is impossible to estimate the unknown

Every software is unique, and it is impossible to estimate a software accurately, when it’s being done for the first time. Even if the requirements are given, it is really hard to estimate a complex system that is going to be built with the given requirements.

Software can be programmed in so many different ways, and usually design decisions, which are not known during the time of estimation, have a huge impact on the duration of the project.

There are, of course, different kind models and methods to make the estimates more accurate, but even with the perfect method, the estimates are still only guesses, because of all the things that are unknown when the estimates are needed, which is usually before the development starts.

2. Estimates are usually optimistic

Most programmers make optimistic estimations. They either think they are more productive than they actually are, or they do not understand the complexity of the software.

This usually leads to padding. The person who receives estimates from the programmers might multiply the estimates with a magic number just to make the estimates less optimistic. This is also very bad, because everyone doesn’t make optimistic estimations.

3. Estimated time is always used

Most programmers also tend to spend the allocated time on a task. If something is estimated to take two days, the programmer makes sure that it takes two days. Even if he finishes early, he will tune and polish his solution, or just slack off, until the allocated time is spent.

This creates a situation, where nothing gets done faster than the estimates, but some things will take longer than the estimates.

4. Business relies on estimations too heavily

Product launches are scheduled based on estimates. Trade shows are booked based on estimates. In some companies the whole sales and marketing departments rely so heavily on estimations that any kind of delay will cause major problems for the company.

5. A lot of time is spent on things that are not estimated

Even if the estimates are perfect, a lot of time must be spent on things that are not estimated. Programmers need to do some maintenance for older versions, someone gets sick, and new tasks come up during the project.

Many companies add another padding for these things, but it does not make the art of estimation any better. If estimates are based on adding padding, and padding on top of guesses, it does not sound something that can be relied on very much.

6. Estimates are not treated as estimates

People do not understand the meaning of the word estimate. It should be taken literally, but the true meaning of the word is not understood nor is it respected. There shouldn’t be too many plans that rely on the estimates. If things that have estimates depend on other estimated things, it creates a chain reaction of delays, when an estimate cannot be reached.

7. Estimates do not consider productivity variations between programmers

This adds another level of difficulty for estimations. In traditional industry, you know the speed of the average bridge builder, but programmers differ so much in productivity that it is impossible to estimate accurately something when you have two unknown variables: the speed of development, and the required amount of work.

The situation is not that bad when programmers estimate their own work, because they might have a good guess on their own productivity, but when someone else does the estimation for the programmers, they could get equally believable numbers with a Stetson-Harrison method.

8. Changes in requirements do not reflect on estimations

Most projects have changes in requirements through out the project, but the estimations for the whole project are not changed. Every single feature added to project must have an effect on the estimates, otherwise the whole process of estimating things is a complete joke.

9. Truth is told when it’s too late

When programmers make their own estimations, they blindly believe that the estimates can be reached and the software will be finished on time. They won’t accept that their estimates were optimistic, until very late in the project, when telling the truth is already too late.

10. Estimates are not updated when they cannot be reached

When estimates are not reached, other estimates should also be corrected, because missing estimates is usually a sign of optimistic estimation. However, in these situations programmers blindly believe that they can do the rest of the tasks faster to make up for the lost time, when the opposite is usually true.

11. Programmers are blamed when estimates cannot be reached

When the whole success of the company depends on estimates, someone must be blamed when the estimates cannot be reached. Usually the finger is pointed to the people, who could not keep up with the estimates: the programmers. This will create a very unhealthy work environment, and programmers will pad the estimates just to keep their jobs safe.

12. Wrong people do the estimates

Estimates should be made by the programmers themselves. Sometimes team leads can do the estimates for them, but the game is lost, if someone with an MBA does the estimates. Run and don’t look back, if this is happening in your company.

  • Share/Bookmark